Project Managment

Read Complete Research Material

PROJECT MANAGMENT

Project management



Project management

Scope Statement

In the given case, we have to manage a fashion show for Dona Prima International. The work break down structure and Gantt Chart for this project is created so that the project can be made successful (Kreiner, 2005, 25).

Organizational work breakdown structure

Organization Breakdown Structure (also known as Organizational Breakdown Structure) or OBS is a hierarchical form describing the established organizational structure for project planning, resource supervision, time and expense tracking, cost allocation, revenue/profit reporting, and work management.

WBS

Fashion shows are fun and creative way of highlighting some of the ethical issues surrounding the fashion industry. There is a lot to be considered so it is well worth planning ahead. Organising a fashion show can be very time consuming and there is a great deal of hard work involved. However, on the day, when the buzz and excitement of the show take over, it is all worthwhile (Midler, 2005, 363).

Activities

Duration

Start

Finish

Cost

Work

Fashion Show

22 days

11/1/2011 8:00

11/30/2011 17:00

£ 18.13

345.8 hrs

 

22 days

11/1/2011 8:00

11/30/2011 17:00

£ 18.13

345.8 hrs

Project Initiation

9.25 days

11/1/2011 8:00

11/14/2011 10:00

£ 18.13

22.4 hrs

Perform fashion show scheduling

0.5 hrs

11/1/2011 8:00

11/1/2011 8:30

£ 15.00

1.5 hrs

Stage Arrangements

0.25 hrs

11/1/2011 8:30

11/1/2011 8:45

£ 0.00

0.5 hrs

Board Approval

1 hr

11/1/2011 8:30

11/1/2011 9:30

£ 0.00

1 hr

Invitation to Fashion Designers

0.2 hrs

11/1/2011 9:30

11/1/2011 9:42

£ 3.13

0.4 hrs

Dresses Finalization

0.5 hrs

11/1/2011 9:30

11/1/2011 10:00

£ 0.00

1 hr

Interviews

0.75 days

11/1/2011 10:00

11/1/2011 17:00

£ 0.00

12 hrs

Contarctor Appointment

0.5 hrs

11/11/2011 16:30

11/11/2011 17:00

£ 0.00

0 hrs

Project Charter Development

2 hrs

11/14/2011 8:00

11/14/2011 10:00

£ 0.00

6 hrs

Fashion Show Planning

0.71 days

11/1/2011 10:00

11/1/2011 16:42

£ 0.00

7.4 hrs

Fashion Show Cracker Development

2 hrs

11/1/2011 10:00

11/1/2011 12:00

£ 0.00

4 hrs

Fashion Show Review

3 hrs

11/1/2011 13:00

11/1/2011 16:00

£ 0.00

3 hrs

Change Control Procedures Agreement

0.2 hrs

11/1/2011 16:00

11/1/2011 16:12

£ 0.00

0.4 hrs

Fashion Show Approval

0.5 hrs

11/1/2011 16:12

11/1/2011 16:42

£ 0.00

0 hrs

Analysis

5.04 days

11/1/2011 16:42

11/8/2011 17:00

£ 0.00

88 hrs

Fashion Show Review Analysis

3 days

11/1/2011 16:42

11/4/2011 16:42

£ 0.00

72 hrs

Fianlize Fashion Show

2 days

11/7/2011 8:00

11/8/2011 17:00

£ 0.00

16 hrs

Design

5 ...