MANAGEMENT TECHNIQUES

Application of Management Techniques

Application of Management Techniques

1.PRODUCE A COST PLAN AND DETERMINE THE LENGTH OF THE CONTRACT FROM THE ATTACHED BILL SUMMARIES FOR YOUR DESIGN AS ALLOCATED TO YOU.

This report highlight the realisation of the foundations, the ground floor, the roof and the façade, part of the Heath and constructed suite in the Mountbatten centre restructuration. This is to be read in conjunction with the volume 23 reports and after the reading of the volume 1 and 22.

2.Prepare an Estimated Cost/Time Schedule for your scheme. (P12 Part)

In order to reach a feasible solution, the following parts have been covered, The identification of problem and constraints, the conceptual Design , the detailed design, the project management which include the bill of quantities, the programme , the environment issues and the method statement .

3.Prepare a Method Statement from the Drawings and Bill of Quantities for one block of your allocated substructure.

Proposed design

To realise a concept, first of all it is important to highlight the key requirement of the brief in order to design the project in concordance with the existing problems.

4.Prepare a Bar Chart from your Method Statement.

Material choice

The type of foundation chosen is the Bored Piles installed by (auger injected Piles).

First of all pile have been chosen because of the water level, and the poor bearing capacity of the soil until 2 m 40.

”The continuous flight auger drilling offer an efficient, rapid solution for predominantly lightly loaded structures” (Bachy soletanche, 2006), like the Health and Constructed suite project with a light steel structure (Volume 23, GWENA, 2006).

5.Produce a Labour on Site Programme from your Bar Chart and Method Statement.

Foundation dimension

Pile will have a maximum of 750 mm diameter and 30m length (Calculation, part ''') and will be spaced of a minimum length of 2. 49m. (drawing MCR 23).

6.Produce a Plant on Site Programme from your Bar Chart and Method Statement.

Task 3 Foundation structure

Problem taken in consideration

As highlighted in the key requirement in the foundation part (see above)

material choice

Pile cap and ground beam will be realised using a backater.

The Concrete use in this foundation structure and as well in the pile foundation is a concrete grade C 30, sulphate resisting because of the polluted soil and the water attendance.

Foundation dimension

(See on drawing, MCR 23)

7.Produce a Materials Requisition from your Bar Chart and Method Statement.

Planning of the foundation realisation

This planning will follow the pile realisation planning. Obviously the drying time need to be finished.

Ground floor slab

Problem taken in consideration

The ground floor has to support the load of a reception area with a maximum span of 5m30

The construction site must be clean as good as possible. Indeed a clean construction avoids accidents.

Re-established quickly the Mountbatten centre to avoid that the centre loose customer.

material choice

Precast slabs have been chosen.

8.Produce a Materials Bin Card for the major materials used from your Bar Chart, Method Statement, Materials Requisition and Materials Received.

First of all “time-consuming activities such as propping, shuttering and concrete pouring are virtually ...