Q1. In your opinion, can you justify the contracting officer's request for a modification? Why or why not? Explain in detail.

In my opinion the contracting officer's request for modification is valid for the cost adjustment. It is due to the fact because either the contractor or the government may propose to modify a contract on the basis of valid stipulations. If a contractor requests a modification he must provide a signed request explaining the modification and its projected effect on the contract. According to the given scenario the contractor ...