The More Integrated And Collaborative Your Team Is, the More Successful Your Projects Should Be
by
Acknowledgement
I would like to take this chance for thanking my research facilitator, friends & family for support they provided & their belief in me as well as guidance they provided without which I would have never been able to do this research.
Declaration
I, (Your name), would like to declare that all contents included in this thesis/dissertation stand for my individual work without any aid, & this thesis/dissertation has not been submitted for any examination at academic as well as professional level previously. It is also representing my very own views & not essentially which are associated with university.
Abstract
In this study we try to explore the concept of “Integrated Project Delivery (IPD)” in a holistic context. The main focus of the research is on “Integrated Project Delivery (IPD)” and its relation with “Integrated Project Team”. The research also analyzes many aspects of “Integrated Project Delivery (IPD)” and tries to gauge its effect on the efficiency of the project teams in delivery the project. This research investigates how IPD achieves relational contracting through traditional project management methods. By investigating the case study of the OUC project, the research further explored how IPD fostered construction innovation and improved overall project delivery.
Table of Contents
ACKNOWLEDGEMENTII
DECLARATIONIII
ABSTRACTIV
Introduction1
Problem Statement/ Purpose of the Research2
Research Methodology4
Use of a Case Study5
Research Objectives5
Research Questions6
CHAPTER 2: LITERATURE REVIEW7
Theoretical Framework7
Problematic Issues in the AEC Industry8
Relational Contracting9
Classical Contracts and Neoclassical Contracts10
Models and Techniques12
Criteria of Selection for National Museum of Australia Construction Alliance14
Integrated Project Delivery (IPD)19
Background20
IPD Process vs. IPD, Inc.20
Achieving Relational Contracting through Traditional Project Management Methods21
Two Primary Principles21
Selection of PTMs22
Determination of Lead Position23
Development of Compensation Structure23
Implementation of Off-site Prefabrication25
Continuous Improvement through Learning26
CHAPTER 3: RESEARCH METHODOLOGY27
Research Design27
Literature Search27
Research Strategy28
Case Study28
Case Study: The Orlando Utilities Commission North Plant29
OUC North Plant Project29
Schedule Performance30
Budget Performance31
Organizational Structure31
Innovation32
Original Plan: Running Conduit Overhead33
Problems Encountered34
Challenges for Installing Conduit Underground34
The Innovative Idea35
Implementation and Outcomes36
CHAPTER 4: DATA ANALYSIS OF THE CASE STUDY38
Objectives38
Data Collection and Analysis38
Conclusion40
CHAPTER 5: CONCLUSIONS41
Contributions to Knowledge41
Clarification of Relational Contracting41
Introduction of IPD42
Introduction of IPT42
Development of Traditional Project Management Methods to Achieve Relational Contracting43
Identification of Outcomes45
Visualization of Innovation Process46
Deficiencies of IPD46
REFERENCES49
APPENDIX55
List of Figures
Figure 1: Characteristics of Classical and Neoclassical Contracts………………………..17
Figure 2: Characteristics of Relational Contract (Cheung et al. 2006)……………………19
Figure 3: Project Alliance Compensation Model (Ross 2003)……………………………20
Figure 4: The Five Big Ideas (Lichtig 2005)………………………………………………23
Figure 5: Major Project Participants in the OUC Project………………………………….39
CHAPTER 1: INTRODUCTION
Introduction
The success of a construction project lies in meeting schedule, cost and quality objectives in a way that benefits both the project teams and the client. However, it is common to see the lack of collaboration between project participants thwarts these goals and finally leads to dissatisfaction on behalf of both contractors and client (Colledge 2005). In the Architecture-Engineering-Construction (AEC) industry, traditional contracting approaches (e.g., design-bid-build) have caused four major problems (Matthews and Howell 2005): (1) holding back good ideas, (2) stifling collaboration and innovation, (3) inhibiting effective coordination, and (4) hampering global optimization. For this reason, an increasing number of construction practitioners have recognized the necessity to shift ...