This is the Work Breakdown (WBS) structure based on the project requirement document. This project plan encompasses five major activities and the sub tasks associated with the project.
S. No.
Activity Name
Task Name
% Completion
Start Date
Finish Date
Resource
Project Duration (days)
Precedent task
1
Defining Project
Studying the requirements
100%
1-7-2008
8-7-2008
Administration
7
--
Installation of new production line
100%
10-8-2008
30-8-2008
Operations Department
20
7-8-2008
Designing of a procurement procedure
100%
11-7-2008
14-7-2008
Logistics and Procurement
3
8-7-2008
2
Team Formation
Determining area of expertise and hiring
100%
9-7-2008
18-7-2008
Human Resource
9
1-7-2008
Designing Contracts
100%
1-8-2008
7-8-2008
Human Resource
7
14-7-2008
Task Assignment
100%
20-8-2008
21-8-2008
Operations Department
2
18-7-2008
3
Project Planning and Estimation
Project planning for different phase of project execution