Inf 342 Week 3 Assignment 1




INF 342 WEEK 3 assignment 1

INF 342 WEEK 3 assignment 1

This is the Work Breakdown (WBS) structure based on the project requirement document. This project plan encompasses five major activities and the sub tasks associated with the project.

S. No.

Activity Name

Task Name

% Completion

Start Date

Finish Date

Resource

Project Duration (days)

Precedent task

1

Defining Project

Studying the requirements

100%

1-7-2008

8-7-2008

Administration

7

--

Installation of new production line

100%

10-8-2008

30-8-2008

Operations Department

20

7-8-2008

Designing of a procurement procedure

100%

11-7-2008

14-7-2008

Logistics and Procurement

3

8-7-2008

2

Team Formation

Determining area of expertise and hiring

100%

9-7-2008

18-7-2008

Human Resource

9

1-7-2008

Designing Contracts

100%

1-8-2008

7-8-2008

Human Resource

7

14-7-2008

Task Assignment

100%

20-8-2008

21-8-2008

Operations Department

2

18-7-2008

3

Project Planning and Estimation

Project planning for different phase of project execution

95%

13-7-2008

28-7-2008

Research and Development

15

8-7-2008

Time span and cost estimation of Project

80%

28-7-2008

30-7-2008

Project Management

2

28-7-2008

Risk assessment of the project

85%

2-8-2008

18-8-2008

Project Management

16

28-7-2008

4

Creating the Product

Researching the ...