CIVIL ENGINEERING MATHEMATICS
Civil Engineering Mathematics
Civil Engineering Mathematics
Answer 1:
The total time required for fixing bars of all diameters is: time in hours of month 1 + time in hours of month 2
539 labor hours + 375 labor hours
914 labor hours
All in tons
10 mm bars
16mm bars
20mm bars
Total
Month 1
8
12
15
35
Month 2
6.9
9.7
5
21.6
Total
14.9
21.7
20
56.6
10mm bars
Time required for 10mm bars: (total tones of 10 mm bar/ total tons of bars fixed) * total labor hours
(14.9/56.6) * 914
240.6 labor hours
240 hours and 36 minutes for 14.9 tons
16.1 hours per ton
16 hours 6 minutes per ton of 10 mm bars.
16mm bars
Time required for 16mm bars: (total tones of 16 ...
Related Ads
- www.researchomatic.com...
Free research that covers a network engineer ...
- www.researchomatic.com...
[Analysis of Civil Engineering Surveying In M ...
- www.researchomatic.com...
Free research that covers a quality engineer ...
- www.researchomatic.com...
Free research that covers nature of work engineer ...
- www.researchomatic.com...
Structural engineering is usually considered ...
The template
footersearch could not be loaded. HTTP Status code: 0