2-1 Basic Estimating Problem
Equipment Costs
$ 15000 $ 35000 $ 50000
Electrical Hook up
$ 400 $ 25 $ 10000
Controls for each piece of equipment
$ 2 $ 600 $ 1200
Start up Material
3700
$ 2.7 per pound
$ 9990
Total Equipment/ Material
$ 71190
Two maintenance specialist for 2days 8hrs
32 hrs
$ 35 per hour
$ 1120
Contract labor fixed Cost
$ 7,500 $ 7500
Installation/ Labor
$ 8620
Engineering costs Equipment/ Materials
15 %
$ 0.15 $ 10678.5
Inspections is to be labor
3 %
$ 0.03 $ 258.6
General and Admin Eqip/ Material & Labor
5 %
$ 0.05 $ 3990.5
Total project ...