2-1 Basic Estimating Problem

Equipment Costs

$ 15000 $ 35000 $ 50000

Electrical Hook up

$ 400 $ 25 $ 10000

Controls for each piece of equipment

$ 2 $ 600 $ 1200

Start up Material

3700

$ 2.7 per pound

$ 9990

Total Equipment/ Material

$ 71190

Two maintenance specialist for 2days 8hrs

32 hrs

$ 35 per hour

$ 1120

Contract labor fixed Cost

$ 7,500 $ 7500

Installation/ Labor

$ 8620

Engineering costs Equipment/ Materials

15 %

$ 0.15 $ 10678.5

Inspections is to be labor

3 %

$ 0.03 $ 258.6

General and Admin Eqip/ Material & Labor

5 %

$ 0.05 $ 3990.5

Total project ...