1. Use Microsoft Project to develop the project schedule
Note: [MS Project file is attached]
2. Critical Path Method
The most widely used scheduling technique is the critical path method (CPM) for scheduling, often referred to as critical path scheduling. This method calculates the minimum completion time for a project along with the possible start and finish times for the project activities. Indeed, many texts and managers regard critical path scheduling as the only usable and practical scheduling procedure. Computer programs and algorithms for critical path scheduling are widely available and can efficiently handle projects with thousands of activities.
With an activity-on-branch network, dummy activities may be introduced for the purposes of providing unique activity designations and maintaining the correct sequence of activities. A dummy activity is assumed to have no time duration and can be graphically represented by a dashed line in a network. Several cases in which dummy activities are useful are illustrated in following figure. In fig (a), the elimination of activity C would mean that both activities B and D would be identified as being between nodes 1 and 3. However, if a dummy activity X is introduced, as shown in part (b) of the figure, the unique designations for activity B (node 1 to 2) and D (node 1 to 3) will be preserved. Furthermore, if the problem in part (a) is changed so that activity E cannot start until both C and D are completed but that F can start after D alone is completed, the order in the new sequence can be indicated by the addition of a dummy activity Y, as shown in part (c). In general, dummy activities may be necessary to meet the requirements of specific computer scheduling algorithms, but it is important to limit the number of such dummy link insertions to the extent possible.
3. a)
Additional Miles stones
i)
Additional Project Milestone Log
Task
Milestone
Completion Date
Task 1
Personal and project calendars
March 2012
Task 2
Description of project scope
May 2012
Task 3
Project risks
June, 2012
Task 4
Lists of activities and resource requirements
August, 2012
ii)
Additional Project Milestone Log
Task
Milestone
Completion Date
Task 1
analyze and document the specifications for the required functionality
June 2012
Task 2
design, implement, test and operate the entire system
August 2012
3. b)
i) latest date when you need to contact is 2/28/2012
ii) latest date when you need to contact is 5/25/2012
4) Memo
To Mr. Brown ,
The expected completion date of the project (M9) is 8/3/2012. The duration of the project is approx. 149 working days. Holidays are excluded. The factors that cause the project to require the estimated length of time includes:
Lack of Clarity in the Scope of the Project
The Scope Statement, once completed, becomes the basis for future project decisions including, in particular, the criteria used to determine if the project (or phase of the project) has been completed successfully. Essentially, this document will form the basis for an agreement between the project team, the project customer and the project sponsor, by identifying ...