[Effective Risk MaNagement in Construction Project]
by
ACKNOWLEDGEMENT
I would take this opportunity to thank my research supervisor, family and friends for their support and guidance without which this research would not have been possible.
DECLARATION
I, [type your full first names and surname here], declare that the contents of this dissertation/thesis represent my own unaided work, and that the dissertation/thesis has not previously been submitted for academic examination towards any qualification. Furthermore, it represents my own opinions and not necessarily those of the University.
Signed __________________ Date _________________
ABSTRACT
Compared with many other industries, the construction industry is subject to more risk due to the unique features of construction activities. Risk management aims at identifying sources of risk and uncertainty, determining their impact, and developing appropriate management response. A systematic process of risk management has been divided into risk classification, risk identification, risk analysis and risk response. The ability of a fuzzy system to explain its reasoning process is shown to have definite applicability within the field of risk analysis. Also fuzzy set theory is highly subjective and related to inexact and vague information which we deal in construction projects. This paper describes the development of a fuzzy risk analysis model to assess the risks associated with construction projects. At the end of paper, the proposed model is used to assess the associated risk with a construction operation based on evaluations of three evaluators. The results derived from this model indicate a systematic and effective way for risk analysis. Contingency estimating and management are critical management functions necessary for successful delivery of construction projects. Considering its importance, academics and industry professionals proposed a wide range of methods for risk quantification and accordingly for contingency estimating1. Considerably less work was directed to contingency management including risk mitigate during a project. Generally, there are two types of risks; (i) known risks which can be identified, evaluated, planned and budgeted for and (ii) unknown risks which may occur. These risks require a cost and time contingency, even if they were not planned for, in order to mitigate their impact in an orderly manner. In this respect, the importance of contingency management is critical in view of increasing project complexity and difficulty of estimating and/or allocating sufficient contingencies to mitigate risks encountered during project execution. This paper focuses on the contingency management from two perspectives; estimation and depletion of contingency over project durations.
TABLE OF CONTENTS
ACKNOWLEDGEMENTII
DECLARATIONIII
ABSTRACTIV
CHAPTER 1: INTRODUCTION8
CHAPTER 2: LITERATURE REVIEW10
Classification Of Risks Associated With Construction Projects10
Reasons for using fuzzy risk analysis for construction projects11
Fuzzy Weighted Average13
Competition Studies in Construction18
Classification of Bidding Models and Strategic Studies19
Original Work by Friedman21
Empirical Tests22
Multiple Regression Techniques24
Internal Conditions, Market Conditions, and Competitors25
Market Conditions26
Go/No-go Decision29
Other Approaches31
Missing Concept in Competition Studies in Construction33
Competition and Mode of Competition34
Empirical Findings36
Studies in Economics and Organization Theory38
Size Distribution of Firms40
Approaches Using Long-run Average Cost Curves41
Equilibrium Approaches42
Evolutionary Approaches42
Discussion and Lessons from Other Competition Studies43
Organizational Culture45
Organizational Risk Attitude48
Strategic Management Studies50
Risk-return Association50
Diversification52
Limits of Empirical Studies54
Characteristics of the Construction Industry55
Fragmentation56
High Entry and Exit Rates57
Derived Demand58
High Risks to Contractors59
Risk and Competition, the Unchanged Characteristics60